US 41 Project:
Construction outlook for 2009
The US 41 Project will expand and
improve 31 miles of freeway in Brown and Winnebago counties. This year,
significant work begins in Winnebago County where WisDOT will launch an
aggressive construction schedule that will run through 2016.
One project for water retention ponds in Brown County was part of the
March letting schedule. However, numerous other projects
will soon be available for bid, with the majority in Winnebago County.
Included is a brief summary of upcoming opportunities, with project ID,
month of let, project description, and DBE goal, if determined:
- #1120-11-71: May let: Witzel
Overpass/Washburn Street: DBE goal 7%
- Construction of new grade
structure across US 41 from Fountain Avenue to Snell Road.
- #1120-11-72: May let: Fountain/Snell
Road Overpass: DBE goal 10%
- Construction of new grade
structure across US 41 from Fountain Avenue to Snell Road.
- #1120-11-73: May let: US 45/Fernau/Lake
Butte des Morts Drive Roundabout: DBE goal 12%
- Construction of multi-lane
roundabout on US 45 at the intersection of Fernau Avenue and Lake
Butte des Morts Drive.
- #1120-11-74: June let: US 41 Grading
and Lake Butte des Morts Drive Overpass: DBE goal 10%
- Grading US 41 southbound into Lake
Butte des Morts; construction of Lake Butte des Morts Drive
structure over US 41; and grading in US 41/45 Interchange.
- #9202-07-77: June let: Brown County
Razing and Removing: DBE goal 20%
- Razing and removing buildings in
preparation for US 41 work.
- #1120-11-79: June let: Winnebago
Couny Razing and Removing: DBE goal 20%
- Razing and removing buildings in
preparation for US 41 work.
- #1120-09-73: June let: US 41/114
Ramp Terminal Improvements: DBE goal being studied.
- Construction of dual left-turn
lanes at exit ramp terminals.
- #1120-10-76: June let: WIS 26 NB/SB
Crash Investigation Sites: DBE goal being studied.
- Construction of crash
investigation sites on exit ramps of US 41/WIS 26 interchange.
- #1120-10-75: July let: Dual Left
Turn Lanes US 41/WIS 44: DBE goal 12%
- Construction of dual lane lefts at
exit ramp terminals and spot concrete repair on WIS 44 between the
ramps.
- #1120-09-82: July let: Wetland
Mitigation Site west US 41, south of WIS 76: DBE goal 13%
- Construction of wetland mitigation
site for the US 41 project.
- #1120-11-80: December let: Washburn
Street Sidewalk: DBE goal 18%
- #1120-11-81: December let: Washburn
Street Lighting: DBE goal 12%
- #1120-09-75: December let: WIS 76
NB/SB Crash Investigation Sites: DBE goal being studied.
- Construction of crash
investigation sites on exit ramps of US 41/WIS 76 interchange.
Mandatory pre-bid meetings will be held
for all US 41 contracts in an effort to increase DBE participation. For
more information contact: Craig Treadway, P.E., WisDOT, NE Region at
(920) 492-0142.
|