Wisconsin Department of TransportationDBE CONTRACTING UPDATE

News for Disadvantaged Business Enterprise firms and stakeholders

May 2009

Home | Calendar | Stats line

 

 

I-94 North-South Freeway update

Eight contracts for the I-94 North-South Freeway project have indicated commitments to meet or exceed the DBE goals on their projects:

  • 27th Street Bridges, Milwaukee County: Zenith Tech; Goal: 10%; Commitment: 11.76%
  • Airport Spur westbound bridge, Grange Ave. Overpass and College Ave Interchange, Milwaukee County: Hoffman; Goal: 10%: Commitment: 11.86%
  • Traffic Mitigation, Rawson Ave; 13th Street and WIS 38; WIS 38 and WIS 119, Milwaukee County: J & A Pohl: Goal: 15%: Commitment: 29.93%
  • College Avenue Intersection, Milwaukee County: Payne and Dolan; Goal: 15%: Commitment: 15.23%
  • Traffic signal upgrades and modifications, Milwaukee County: Habermehl Electric; Goal: 15%: Commitment: 95.60%
  • County E Frontage Roads, Kenosha County: Hoffman; Goal: 10%: Commitment: 12.10%
  • County C Frontage Roads, Kenosha County: Michels Corporation; Goal: 12%: Commitment: 12.05%
  • WIS 158 Frontage Roads, Kenosha County: Hoffman; Goal: 12%: Commitment: 12.72%

Three contracts have been awarded as part of the American Recovery and Reinvestment Act (ARRA) from a special letting held on April 28. The following contractors have been awarded those projects:

  • County G Interchange, Racine County: Zignego, DBE Goal 16%
  • WIS 50 to IL State Line mainline including County C Interchange, Kenosha County: Walsh Construction Group, DBE Goal 16%
  • CTH G Fencing, Racine County: Highway Landscapers, DBE Goal 25%

The following opportunities are currently advertised for the letting on June 9, 2009.

14. N-S Freeway, Layton Avenue Bridge, B-40-820; Milwaukee County; 1030-20-74, WISC 2009 449; I-94; 0.000 Miles; Steel Fabrication.
Guaranty Required $75,000.00
Estimate of Principal Items: Fabricate Bearing Pads, 36 Each; Fabricate Fixed Bearing Assemblies, 12 Each; Fabricate Expansion Bearing Assemblies, 12 Each; Fabricate Structural Steel, 2,195,000 Each; Painting Polysiloxane, 1 Lbs.
DBE Goal: 15 % Contract Completion Date: June 15, 2010
For further information, contact: Bill Mohr, (262) 548-5666.

15. N-S Freeway, Bolivar Avenue Realignment; Milwaukee County; 1030-21-74, WISC 2009 450; Local; 0.000 Miles; Milling, Grading, Base Aggregate, Asphalt Paving, Concrete Paving, Curb and Gutter, Sidewalk, Underground Utilities, and Pavement Marking.
Guaranty Required $40,000.00
Estimate of Principal Items: Excavation Common, 1,013 CY; Base Aggregate Dense, 615 Ton; Concrete Pavement, 1,195 SY; Pavement Marking Epoxy, 350 LF; Incentive Strength Concrete Pavement, 500 Dol; Storm Sewer Pipe Reinforced Concrete, 31 LF 12", 172 LF 48"; Concrete Curb and Gutter, 620 LF; Concrete Sidewalk, 2,855 SF; Asphaltic Surface, 72 Ton; Removing Asphaltic Surface Milling, 31 SY; Asphalt MS, SS, CSS, 10 Gals; 4-Duct Conduit Cement Encased 4-Inch Rigid Nonmetallic Conduit, 270 LF; Ductile Iron Water Main, 202 LF; Ductile Iron Hydrant Branch, 8 LF; Sanitary Sewer, 179 LF.
DBE Goal: 20 % Contract Completion Date: October 15, 2009

Mandatory Pre-Bid Meeting

Prospective bidders are required to attend a Mandatory Pre-Bid Meeting on May 28, 2009 from 1 PM to 3 PM in the Wisconsin Conference Room of the Milwaukee office of the Wisconsin Department of Transportation located at 1001 W. St. Paul Avenue in Milwaukee, Wisconsin.

No meeting minutes will be prepared, but a published response will be sent out addressing all questions raised at the meeting.

For further information, contact: Bill Mohr, (262) 548-5666.

16. N-S Freeway, Utilities Contract; Milwaukee County; 1030-21-78, WISC 2009 451; I-94; 0.000 Miles; Base Aggregate, Asphalt Paving, Concrete Paving, Curb and Gutter, Sidewalk, and Underground Utilities.
Guaranty Required $100,000.00
Estimate of Principal Items: Base Aggregate Dense, 265 Ton; Breaker Run, 97 Ton; Concrete Pavement, 123 SY; Construction Staking, 1 LS; Storm Sewer Pipe Reinforced Concrete, 330 LF 12", 20 LF 36", 30 LF 54", 664 LF 60"; Concrete Curb and Gutter, 62 LF; Concrete Sidewalk, 190 SF; Asphaltic Surface, 85 Ton; Asphalt MS, SS, CSS, 7 Gals; Backfill Controlled Low Strength, 8,669 CY; Relaid Storm Sewer, 90 LF; Intermediate Jacking Station, 2 Each; Micro Tunneling Reinforced Concrete Pipe, 5,161 LF; Ductile Iron Water Main, 708 LF; Steel Casting Pipe, 340 LF.
DBE Goal: 12 % Contract Completion Date: March 10, 2010

Mandatory Pre-Bid Meeting

Prospective bidders are required to attend a Mandatory Pre-Bid Meeting on May 28, 2009 from 1 PM to 3 PM in the Wisconsin Conference Room of the Milwaukee office of the Wisconsin Department of Transportation located at 1001 W. St. Paul Avenue in Milwaukee, Wisconsin.

No meeting minutes will be prepared, but a published response will be sent out addressing all questions raised at the meeting.

For further information, contact: Bill Mohr, (262) 548-5666.