Wisconsin Department of TransportationDBE CONTRACTING UPDATE

News for Disadvantaged Business Enterprise firms and stakeholders

November 2009

Home | Calendar | Stats line 

 

 

Stats line - a look at the numbers on key projects

The DBE Contracting Update continues to track DBE contracting and labor data from several high profile projects.  Projects may be added or moved from this feature over time as they progress from planning to completion


I-94 North/South Freeway Project
Kenosha, Racine & Milwaukee Counties
www.sefreeways.org 

 

Design (without ARRA)

Committed dollars (contracts)
  Total - $91.88 million
  DBE - $26.43 million
  DBE share - 29%

Dollars expended
  Total - $59.27 million
  DBE - $15.45 million
  DBE share - 26%

 

Design (with ARRA)

Committed dollars (contracts)
  Total - $98.07 million
  DBE - $27.69 million
  DBE share - 28%

Dollars expended
  Total - $60.31 million
  DBE - $15.37 million
  DBE share - 25%

 

Construction (without ARRA)

Committed dollars (contracts)
  Total - $7.04 million
  DBE - $2.07 million 
  DBE share - 29%
Dollars expended
  Total - $1.74 million
  DBE - $53,000 
  DBE share - 30%

 

Construction (with ARRA)

Committed dollars (contracts)
  Total - $6.19 million
  DBE - $1.26 million 
  DBE share - 20%
Dollars expended
  Total - $1.03 million
  DBE - $2,200 K 
  DBE share - 22%

 

Construction Contractor 

Committed dollars (contracts)
  Total - $147.05 million
  DBE - $18.27 million 
  DBE share - 12%
Dollars expended
  Total - $45.49 million
  DBE - $3.60 million 
  DBE share - 8%

 

Labor employee count

Total employee count 4118
Minority employee count  801
Minority share  19%
Women employee count 133
Women share  3%

 

Labor hours worked

Total hours worked 342,128.1
Minority hours worked  56,166
Minority share  16%
Women hours worked 9799.64
Women share  3%

 

Notes:

  • All data current through September 30, 2009.
  • Data includes consultant work for design and environmental study activities.

US 41 Expansion projects
Brown & Winnebago Counties
www.dot.wisconsin.gov/projects/us41expansion/index.htm
www.dot.wisconsin.gov/projects/us41expansion/brown-index.htm
 

 

Committed dollars (contracts)
  Total - $99.10 million
  DBE - $20.30 million
  DBE share - 20%
Dollars expended
  Total - $34.51 million
  DBE - $4.69 million
  DBE share - 14%

 

 

 

Labor employee count

Total employee count 1,277
Minority employee count  116
Minority share  9%
Women employee count 891
Women share  6%

Labor hours worked

Total hours worked 82,205
Minority hours worked  4098.2
Minority share  5%
Women hours worked 3,436.6
Women share  4%

 

 

Notes:

  • All data current through September 30, 2009.
  • Data includes consultant work for design activities.

Zoo Interchange Study
www.sefreeways.org

 

Committed dollars (contracts)
  Total - $12.66 million
  DBE - $2.84 million
  DBE share - 22%
Expended dollars
  Total - $10.65 million
  DBE - $2.34 million
  DBE share - 22%

 

 

 

Notes:

  • All data is current through September 30, 2009.
  • Data includes consultant work for design and environmental study activities.