Northeast Region weekly construction update
June 13, 2013
The Wisconsin Department of Transportation (WisDOT) NE Region in Green Bay is providing a weekly update on region construction, which includes the counties of Brown, Calumet, Door, Fond du Lac, Kewaunee, Manitowoc, Marinette, Oconto, Outagamie, Sheboygan, and Winnebago.
Construction-related traffic impact exists in the locations listed below. Closures listed are subject to change and are weather-dependent.
Regionwide
Regionwide Deck Sealing Project
Schedule: June to August
Length: N/A
Cost: $0.6 million
Location: Various highways: Brown, Calumet, Outagamie, Winnebago counties
Description: The project involves short term lane and shoulder closures and deck
sealing operations
Traffic impacts: Short term lane and shoulder closures. Some work is at night.
NE Region backbone routes – Beam guard end treatment upgrades
Schedule: April 22 to June 28, 2013
Length: N/A
Cost: $1.2 million
Location: Various highways throughout NE Region
Description: Guardrail removal and installation, grading operations, and traffic
control. There are a total of 56 sites within Brown, Outagamie, Winnebago, Fond du Lac, Calumet and
Manitowoc counties requiring upgrades to beam guard and end treatments. Lane closures will be
changing weekly as sites are completed.
June 10 to June 14: The contractor will continue project work in Fond du Lac
County along US 151 by replacing old beam guard with new at Hwy 49/Dodge County line as well as at
Oak Center Road. Night work will be taking place in Outagamie County along US 41 at Meade Street.
Work will also be taking place in Brown County along US 41 at County S.
June 17 to June 21: The contractor will continue project work in Manitowoc
County along I-43 by replacing old beam guard with new at County XX. Work will also be taking place
in Winnebago County along Hwy 45 at County G and County II.
Traffic impacts: There will be single lane closures in Manitowoc County along
I-43 northbound and southbound from Monday at 6 a.m. to Tuesday 5 p.m. at County XX. There
will be inside lane work on I-43 but there will be one lane open at all times. There will be
shoulder closures in Winnebago County along Hwy 45 at County G and County II northbound and
southbound on Tuesday and Wednesday. There will single lane closures in Winnebago County along Hwy
441 and Hwy 10 eastbound from Tuesday and Wednesday between 7 p.m. to 2 a.m.
Brown County
For information on the US 41 major project, please check the project website.
WIS 160, village of Pulaski
Schedule: May 13 to October 15, 2013
Length of project: 0.63 miles
Cost: $1.4 million
Location: WIS 160 from Brown County/Shawano County line to St Augustine Street.
Description of work: This project involves the reconstruction of WIS 160 from
Highview Street to St. Augustine Street in the village of Pulaski. This project includes storm
sewer placement, curb and gutter, sidewalk, colored aprons, asphalt pavement.
June 10 to June 14: WE Energies was on site placing street lighting from Main
Street to St. Augustine Street. The contractor also placed sidewalk in this same area.
June 17 to June 21: The contractor will continue to place sidewalk from Main
Street to St. Augustine Street. They will also pave the asphalt for WIS 160 from Main Street to St.
Augustine Street.
Traffic impacts: The road will be closed from St. Augustine Street to Highview
Street. The detoured route is WIS 32 to WIS 29.
US 41 Orange Lane to Glory Road, Main Avenue (County G) Interchange
Schedule: March 2012 through June 2013
Length: Mainline 3.5 miles (Orange Lane – Glory Road); Main Avenue (County G) –
0.5 miles (Spirit Way – Lawrence Drive)
Cost: $57 million
Location: Town of Lawrence, city of De Pere, village of Ashwaubenon; Brown County
Description of project: This project will reconstruct US 41 Mainline between
Orange Lane and Glory Road and the reconstruction of the Main Avenue interchange and replacement of
bridges over Ashwaubenon Creek, Main Avenue, and Grant Street.
June 10 to June 14: Contractor continued to pave the outside lanes of US 41
both northbound and southbound. Work began on the placement of the outside southbound barrier
wall north of Scheuring Road. Contractor completed the work on the northbound off-ramp to
Ashland Avenue.
June 17 to June 21: Contractor continues to pave the outside lanes of US 41
both northbound and southbound. Work will begin on the placement of the outside southbound barrier
wall. Contractor will also continue work on the Scheuring Road northbound on-ramp placing curb and
gutter and shoulder.
Traffic impacts: US 41 northbound and southbound shoulders closed from March
5, 2012 to June 21, 2013 from 1.5 miles south of Scheuring Road to Parkview Road. US 41 northbound
and southbound lanes are restricted to 11 feet from 1.5 miles south of Scheuring Road to Parkview
Road with speeds reduced from 65 mph to 55 mph within the project limits and north through the WIS
29 Interchange project. Shoulders will also be closed on the Scheuring Road interchange ramps as
well as the Ashland Avenue and Main Avenue southbound on-ramps. The Scheuring Road westbound turn
lane to US 41 northbound will be closed through June 21. On June 21, the traffic on this ramp
will be switched to the east lane and the Scheuring Road westbound turn lane will be reopened. The
access for eastbound Scheuring will be detoured and will also use the westbound turn lane. The left
lane of the southbound off-ramp to County G will be closed until June 21. There will be lane
closures on eastbound and westbound County G as well as a northbound shoulder closure along Mid
Valley Drive between County G and County EE from June 17 to June 21.
US 41, Grant Street reconstruction
Schedule: May 20 to June 28, 2013
Length of project: 0.13 miles
Description of work: This project consists of excavation common, storm sewer,
breaker run, base aggregate dense, HMA pavement, concrete pavement, concrete curb and gutter,
permanent signing, pavement marking, and lighting.
June 10 to June 14: The contractor was staking and paving concrete.
June 17 to June 21: The contractor will finish concrete paving and begin
shaping and landscaping.
Traffic impacts: The intersection of Grant Street (County EE) and Mid Valley Drive
is closed.
County VK, Ashwaubenon, Brown County
Schedule: April 22 to June 28, 2013
Length of project: 0.11 miles
Description of work: The project work includes grading, common excavation,
base aggregate, concrete pavement, concrete curb and gutter, storm sewer, permanent signing,
pavement marking, traffic signals and all incidental items necessary to complete the as shown on
the plans and included in the proposal and contract.
June 10 to June 14: Electricians drilled bases for signal poles, installed conduit
and pull boxes. Crew continued to pour hand work sections of concrete pavement. Crew worked on
landscaping and installed signing towards the end of the week. Crew was on site forming and pouring
driveways, sidewalk, and curb and gutter.
June 17 to June 21: Crew will pave the transition section early in the week. Crew
will work on landscaping and installing signing. There will be clean up at the site for crew to
install pavement marking midweek.
Traffic impacts: Argonne Street closed to all traffic. County VK (Lombardi Avenue)
has various lane closures. Two lanes of traffic will remain open in both eastbound and
westbound. On June 10 through June 12, one lane will be open in both eastbound and westbound.
There will also be flagging operations for construction vehicles crossing to and from the
median.
US 41/ WIS 29 Interchange Core Project – US 41 major
Schedule: August 2012 to October 2014
Length: 1.6 miles along US 41, 0.8 miles along WIS 29
Cost: $97 million
Location: US 41 (Mason Street to Memorial Drive)/WIS 29 (County J to Taylor
Street)
Description: This project will complete the reconstruction of the US 41 and WIS 29
interchange, converting the interchange by building high speed, free flow flyover ramps, along with
adding capacity to US 41. Included in this project is the construction of 12 bridges, 15 retaining
walls, 30 sign bridges, concrete pavement, asphalt pavement, storm sewer, stormwater detention
ponds and landscaping, while incorporating many community sensitive design features.
June 10 to June 14: Crews continued decking operations at Packerland Drive for new
WIS 29 bridges, and sign bridge construction also continued. Structural steel girders continued to
be set west of US 41 for the future flyover bridge structures, including over both northbound and
southbound lanes of US 41. Grading operations continued along northbound and southbound US 41 in
the Shawano Avenue interchange area, as well as on the new WIS 29 lanes east of Packerland
Drive. Pond construction near the US 41 on northbound ramp at Dousman continued. Asphalt base
along with concrete pavement continued along the future southbound US 41 lanes between Mason Street
and Shawano Avenue.
June 17 to June 21: Crews will continue decking operations at Packerland
Drive for new WIS 29 bridges, and sign bridge construction will also continue. Structural steel
girders will continue to be set west of US 41 for the future flyover bridge structures, including
over the southbound on-ramp to US 41 and over the northbound lanes of US 41. Grading operations
will continue along northbound and southbound US 41 in the Shawano Avenue interchange area, as well
as continue on the new WIS 29 lanes east of Packerland Drive. Pond construction near the US 41
on northbound ramp at Dousman will continue. Asphalt base along with concrete pavement will
continue along the future southbound US 41 lanes between Mason Street and Shawano Avenue. A deck
pour is planned for the first unit of the future northbound US 41 bridge to westbound WIS 29
flyover bridge, which is along the east side of current northbound US 41.
Traffic impacts: A northbound US 41 lane closure and the northbound off-ramp
to WIS 29 planned to be closed on June 12, June 14, June 18, and June 19 for grading. Northbound
and southbound full closures of US 41 are planned for June 13 and June 15 between the on and
off-ramps at WIS 29 to erect steel tub girders. Southbound US 41 will be closed from 7 p.m. to 6
a.m., and northbound will be closed from 9 p.m. to 6 a.m. The US 41 southbound on-ramp from WIS 29
will be closed on June 19 and June 21 from 9 p.m. to 8 a.m. to erect steel tub girders. The
US 41 on-ramp from WIS 29 will be closed on June 18 and June 20 between 7 p.m. to 6 a.m. as
well as a full closure of northbound US 41 between the on-ramps and off-ramps at WIS 29 on those
same dates between 9 p.m. and 6 a.m. to erect steel tub girders.
US 41 Beaver Dam Box Culvert Project - US 41 major
Schedule: April 2013 to May 2014
Length: 0
Cost: $6.9 million
Location: US 41 (Shawano Avenue to Velp Avenue)
Description: This project will complete the construction of the new Beaver Dam box
culvert between Shawano Avenue and Velp Avenue on US 41, a new storm water pond in the northwest
quadrant of US 41 and Velp Avenue, and reconstruct the cul-de-sacs of Island Court and Lone Grove
Avenue.
June 10 to June 14: Crews continued working on the box culvert construction and
grading on the west side of US 41. Crews began grading on the east side of US 41. Crews also
paved the southbound median of US 41.
June 17 to June 21: Crews will continue working on box culvert construction and
grading on the east and west sides of US 41.
Traffic impacts: There will be intermittent southbound lane closures between 7
p.m. and 5 a.m. and northbound lane closures between 8 p.m. and 7 a.m. on US 41.
US 41 Lakeview Drive
Schedule: August 2012 to May of 2013
Length: 0.1 miles
Cost: $3,324,000
Location: Lakeview Drive, Green Bay WI, Brown County
Description: Building retaining walls and reconstruction the Lakeview Drive
Bridge.
June 10 to June 14: Final cleanup work.
June 17 to June 21: Final cleanup work.
Traffic impacts: There will be intermittent southbound lane closures between 7
p.m. and 5 a.m. and northbound lane closures between 8 p.m. and 7 a.m. on US 41.
Leo Frigo Bridge, city of Green Bay/I-43
Schedule: May 2012 to July 2013
Length: 3.5 miles
Cost: $16.8 million
Location: I-43 over the Fox River
Description: Work consists of completing concrete deck surface repair and
placing an asphalt or concrete overlay on I-43 over the Fox River, Atkinson Drive over I-43, and
Military Avenue over I-43; replacing the bridge joints along I-43 over the Fox River and Military
Avenue over I- 43; painting of the steel girders within ten feet of the joint replacements, the box
girders along the arch span, and all steel within the splash zone along I-43 over the Fox River;
concrete pavement repairs along I-43 between Webster Avenue and Military Avenue and along with the
ramps at Webster Avenue and Atkinson Drive; traffic cameras at I-43/Danz Avenue, I- 43/University
Avenue, and I-43/County JJ; dynamic message signs at I-43/Glenmore Road, I- 43/Danz Avenue,
I-43/Military Avenue, and I-43/WIS 54/57; ramp gates at the Webster Avenue and Atkinson Drive
on-ramps to I-43; temporary and permanent storm sewer; beam guard replacement; median concrete
barrier wall; sign replacement; and pavement markings.
June 10 to June 14: Contractor continued to place the permanent pavement markings
along I-43; and they completed the deck repairs and placed half of the concrete overlay on the
Military Avenue Bridge over I-43.
June 17 to June 21: Contractor will continue to place the permanent pavement
markings along I-43; they will finish placing the concrete overlay on the Military Avenue Bridge
over I-43; and they will remove the median crossovers along I-43.
Traffic impacts: Southbound I-43 is reduced to one lane from US 41 to Webster
Avenue and the posted speed limit has been reduced to 55 mph. The on-ramp from Atkinson Drive to
southbound I-43 is closed until late July. Northbound I-43 is reduced to one lane from University
Avenue to Webster Avenue and reduced to 55 mph Monday through Friday. The on-ramp from Webster
Avenue to I-43 northbound is closed until late July. Military Avenue is closed from Wietor Drive to
Hurlbut Street (the bridge over I-43) and will remain closed until early July. The I-43 northbound
off-ramp to Atkinson Drive and the I-43 southbound off-ramp to Webster Avenue is scheduled to be
closed from 6 p.m. to 6 a.m. for one evening the week of June 17. Exact date yet to be
determined.
WIS 29/County U and WIS 29/County VV
Schedule: April to June
Length: 1 mile
Cost: $1 million
Location: At the intersections of WIS 29/County VV and WIS 29/County U in Brown
County.
Description: Construction of J-turns at the WIS 29/County VV intersection and
intersection improvements at WIS 29/County U.
June 10 to June 14: Open WIS 29/County VV J-turns to traffic. Construction will
begin Monday June 10 on WIS 29/County U. Construction activities will include removals, storm
sewer, and base grading.
June 17 to June 21: Continue construction at WIS 29/County U intersection. Work
activities will include storm sewer, base aggregate placement, and curb and gutter.
Traffic impacts: The J-turns at WIS 29/County VV are open to traffic. The
right shoulder at WIS 29/County VV will remain closed on westbound lanes of WIS 29 to allow
contractor to remove the temporary intersection. The median crossover at WIS 29/County U will be
closed to traffic. Traffic attempting to maneuver across WIS 29 median at County U will have to use
the newly constructed J-turns or the WIS 29/WIS 32 interchange. County U adjacent to WIS 29 may be
closed between June 17 and June 21 to allow for "porkchop" island construction. County U closure
will be from Old Wisconsin 29 to Glendale Avenue. Message boards will inform the traveling public
three days prior to the closure.
For more information, visit the project page.
Brown/Outagamie County
WIS 54
Schedule: Late April to late June 2013
Length: 1.0 miles
Cost: $8.74 million
Location: WIS 54 from Oneida to Green Bay, County U to WIS 172
Description: This project involves the realignment of WIS 54 with a new bridge
over Duck Creek and construction of a roundabout at the intersection of WIS 54 and Seminary Road.
Work includes storm sewer, asphalt pavement, construction of a retaining wall, bridge
rehabilitation, lighting, signing, landscaping and pavement marking.
June 10 to June 14: Crews continued rehab work on the old truss structure over
Duck Creek. Crews stained the retaining wall along WIS 54. Electrical crews continued to install
lighting along the south pedestrian path of WIS 54. Landscaping crews began final plantings
along WIS 54. Epoxy overlay operation for the new structure over Duck Creek will begin late in the
week.
June 17 to June 21: Epoxy overlay operations will continue throughout the
week on the new structure over Duck Creek. Asphalt paving of the south path along WIS 54 will
be completed early in the week. Electrical crews will continue working on lighting for the
pedestrian paths along WIS 54. Chain link fence will be installed around the retaining wall
along WIS 54 and around the old structure over Duck Creek. Landscaping crews will continue
final plantings along WIS 54 throughout the week.
Traffic impacts: Traffic along WIS 54 will remain open at all times. Some shoulder
closures may be necessary to complete work but travel lanes along WIS 54 will remain open during
the 2013 construction season.
Main Street, Village of Little Chute
Schedule: May to October 2013
Length: 1.5 miles
Cost: $3.7 million
Location: WIS 96 from Jackson Street to Hayes Street.
Description: This project involves the reconstruction of the WIS 96.
June 10 to June 14: Crews continued installing storm sewer from the intersection
of Sanitorium and WIS 96 and worked towards the west. Crews continued breaking the remaining
concrete pavement. Crews continued clearing and grubbing.
June 17 to June 21: Crews will continue installing storm sewer from the
intersection of Sanitorium and WIS 96 to the intersection of Jackson Street and WIS 96.
Traffic impacts: Traffic will be detoured for the duration of the
project. Traffic heading east on WIS 96 will be detoured onto County N to County OO to WIS 55
to WIS 96. Traffic heading west on WIS 96 will be detoured onto WIS 55 to County OO to County N to
WIS 96.
Calumet County
No state construction projects currently in progress.
Door County
Bayview Bridge
Location: WIS 32/57, Sturgeon Bay, Door County
Schedule: March 4 to July 4
Length of project: 0.3 miles
Description of work: The project includes structural steel repair, bridge
painting, electrical and machinery system upgrades, an overlay of the bridge deck and approaches.
This work is being done to extend the life of the bridge.
June 10 to June 14: Contractor will begin epoxy overlay on north flanking
span, and south bridge span. Painters will begin blasting and painting north bascule leaf.
Electricians will continue work on motors and new actuators for the bascule leafs. Epoxy overlay on
the bridge deck is continuing to be placed this week.
June 17 to June 21: Painters will continue blasting and painting north
counterweight and flanking span sections. Electricians will continue with electrical controls
installation and begin their control and machinery testing.
Traffic impacts: Bridge closed to vehicular traffic and pedestrians – detour
through city of Sturgeon Bay. For more project information, visit the
project web
page.
Fond du Lac County
No state construction projects currently in progress.
Kewaunee County
No state construction projects currently in progress.
Manitowoc County
No state construction projects currently in progress.
Marinette County
No state construction projects currently in progress.
Oconto County
No state construction projects currently in progress.
Outagamie County
No state construction projects currently in progress.
Sheboygan County
WIS 23 – County O, E and Pleasant View Road
Schedule: June to October 2013
Length: 1.2 miles – three intersection rehabilitations
Cost: $2 million
Location: County O to Pleasant View Road, Plymouth
Description of work: Work consists of creating safety enhancements and
rehabilitating three intersections along WIS 23 in the city of Plymouth, Sheboygan County. The
three intersections being reconstructed are: County O, County E and Pleasant View Road. Left turn
lanes are being constructed in the median of WIS 23 at each of these locations. These turn
lanes will restrict the traffic that will be able to cross WIS 23. Traffic approaching from the
north or south (attempting to cross WIS 23) will only be allowed to make a right hand turn movement
onto WIS 23.
June 17 to June 21: The contractor will mobilize to the project site on Monday,
June 17 and will start removals and grading at these locations.
Traffic impacts: Full closures (except for emergency vehicles) of the County O and
Pleasant View intersections will begin on Monday, June 17 at 6 a.m. The outside (right) lane
and outside (right) shoulder closures on WIS 23 east and westbound will also be starting on Monday,
June 17 at 6 a.m. from WIS 67 to WIS 57. WIS 23 closures will conclude at 12 p.m. on Friday,
June 21. Left hand turns through the median on WIS 23 at these intersections will be restricted to
emergency vehicles only. Traffic should utilize County E as a temporary alternate route.
WIS 23 – County M
Schedule: June to October 2013
Length: 0.7 miles – one intersection rehabilitation
Cost: $0.85 million
Location: County M Intersection, town of Plymouth
Description of work: Work consists of creating safety enhancements and
rehabilitating this intersection along WIS 23 in the city of Plymouth, Sheboygan County. County M
is being constructed into a J-turn intersection. Left hand turn lanes are being constructed in the
medians at this location. These turn lanes will restrict the traffic that will be able to cross WIS
23. Traffic approaching from the north or south (attempting to cross WIS 23) will only be allowed
to make a right hand turn movement onto WIS 23.
June 17 to June 21: Traffic control setup to begin.
Traffic impacts: No impacts at this time.
WIS 32
Schedule: June 3 to September 15, 2013
Length: 6.0 miles
Cost: $2 million
Location: WIS 23 to the north village limits of Howards Grove
Description: This project involves the resurfacing of WIS 32. The road
will be milled and resurfaced with increasing more right turn lane capacity at intersection of
County O, Woodland Road, County J, and Playbird Road. In the village of Howards Grove some drainage
structures will be reconstructed or adjusted and curb and gutter sections will be
replaced. The contractor, Northeast Asphalt and its subcontractors will be doing all of the
work. The work involves removals, grading, base, asphalt pavement, storm sewer, sanitary sewer
manholes, erosion control, permanent signing, traffic control, pavement marking, restoration and
all necessary items to complete the work.
June 10 to June 14: Work continues in the village of Howards Grove at the
northeast and southeast quadrants of intersections at County A (College Avenue) and WIS 32 and WIS
32 and WIS 42. The contractor has placed new curb and gutter at these intersections and has begun
placing new sidewalk. By the end of this week all curb and gutter and driveway aprons should be
placed at these intersections in the northeast and southeast quadrants. In the rural section of WIS
32 the old asphaltic surface has been milled. At County O and WIS 32, the work for increased
turn lane expansion for WIS 32 northbound began this week.
June 17 to June 21: The rural section of WIS 32 from WIS 23 to the south village
limits of Howards Grove is scheduled to be paved. Work will continue with the turn lane expansions
at County O and WIS 32 and work for added turn lane expansion at Woodland Road and WIS 32 may
begin. Work in the village of Howards Grove will continue as well at the northwest and southwest
quadrants of intersections at County A and WIS 32 and at WIS 32 and WIS 42. Removal of curb
and gutter, pavement, and sidewalk with some storm sewer work is planned.
Traffic impacts: WIS 32 and all side roads will be open to all traffic during
construction using flagging operations suitable for lane closure. Drivers are advised to slow
down in the rural section of WIS 32 as the road is milled and now consists of a roughened
surface. The shoulders near the intersections at County O, Woodland Road, County J, and
Playbird Road are closed. Bumps are marked with warning signs. Please use caution.
WIS 42
Schedule: June 3 to September 15, 2013
Length: 1.0 miles
Cost: $500,000
Location: Village of Howards Grove from the Pigeon River to the north village
limits
Description: This project involves the resurfacing of WIS 42 within the
village of Howards Grove. The road will be milled and resurfaced with rehabilitation to curb and
gutter and storm sewer. New sidewalk will be installed along WIS 42 within the village. The
contractor, Northeast Asphalt and its subcontractors will be doing all of the work. The work
involves removals, base, asphalt pavement, storm sewer, sanitary sewer manholes, erosion control,
permanent signing, traffic control, pavement marking, restoration and all necessary items to
complete the work.
June 10 to June 14: Work continues in the village of Howards Grove at the
northeast and southeast quadrants of the intersection at WIS 42 and WIS 32. The contractor has
placed new curb and gutter at these intersections and has begun placing new sidewalk. By the end of
this week all curb and gutter and driveway aprons should be placed at this intersection in the
northeast and southeast quadrants.
June 17 to June 21: Work at the northwest and southwest quadrants of the
intersection of WIS 42 and WIS 32 will be getting started. Removal of curb and gutter, pavement,
and sidewalk with some storm sewer work is planned. Concrete work with new curb and gutter,
driveways, sidewalk improvements will also be taking place once removals are complete.
Traffic impacts: WIS 42 and all side roads will be open to all traffic during
construction using flagging operations suitable for lane closure.
I-43 Bridge Painting
Schedule: May 6 to June 24, 2013
Length of project: 0.0 miles
Cost: $710,000
Location: WIS 32 and County KK bridges over I-43
Description: The WIS 32 and County KK bridges over I-43 will have the structural
steel repainted. I-43 will remain open to traffic with single lane closures in both directions. WIS
32 will remain open to two-way traffic during bridge painting operations. County KK will be closed
to traffic during bridge painting operations. During closure, County KK will not be detoured.
Traffic impacts: The left, inside lane of northbound I-43 will be closed down
underneath the County KK bridge. The left, inside lane of southbound I-43 will be closed down
underneath the County KK Bridge. A reduction of the posted regulatory speed limit from 65 mph
to 55 mph will take place on I-43 during the lane closures. The County KK bridge over I-43 will be
closed with no detour. The northbound lane will be opened by noon on Friday, June 14, and the
southbound lane will be opened by noon on Sunday, June 16
WIS 57
Schedule: April to October 2013
Length: 24 miles
Cost: $5.0 million
Location: Sheboygan County to Ozaukee/Sheboygan County line to
Manitowoc/Sheboygan County line
June 10 to June 14: Asphalt milling and paving began between Clearview Road and
WIS 23. Asphalt pavement removal and replacement with concrete pavement completed at several
locations throughout the project. Shoulder gravel was placed between County O and WIS 32.
June 17 to June 21: Asphalt paving to continue between County O and Clearview
Road. Center line rumble strips and lane painting will be placed between County O and WIS
32. Asphalt pavement removal and replacement with concrete pavement will continue at several
locations throughout the project.
Traffic impacts: WIS 57 will remain open to through traffic. Between County K and
County O, single lane closures will occur in areas of work. Between County O and WIS 32, work will
be completed using flagging operations.
Please note: No work will be performed from noon, June 20 to 6 a.m. June 22 for
NASCAR Nationwide Series event at Road America. All lanes of traffic will also be open during this
period.
Winnebago County
WIS 21 and WIS 116, city of Omro
Schedule: June 17 to July 31, 2013
Length: 0.14 miles
Cost: $134,000
Location: WIS 21 and WIS 116 North Junction, city of Omro, Winnebago County
Description: This project involves the milling and re-paving of the asphalt
pavement in the north intersection of WIS 21 and WIS 116 in the city of Omro. Other work includes
removing and replacing curb and gutter, widening asphalt shoulders, installing new storm sewer,
removing and replacing traffic signs and pavement marking, and replacing beam guard.
June 10 to June 14: The contractor will be setting up traffic control devices for
work beginning next week. The contractor will be placing survey stakes for the upcoming work.
June 17 to June 21: Project work will begin this week with the contractor
installing erosion control items, removing existing curb and gutter, installing new storm sewer,
and preparing the shoulder widening areas for asphalt.
Traffic impacts: WIS 21 and WIS 116 will remain open to traffic throughout the
project. The contractor will be required to use flag persons if any lane closures are required.
Spruce Street will be closed to traffic throughout the project
For information on the US 41 major project, please check the project website.
WIS 26 – Breezewood Lane
Schedule: April to October 2013
Length: .66 miles
Cost: $924,721.75
Location: WIS 26 to WIS 21 (WIS 44 median work)
Description: Work consists of replacing the approach slabs, joints, and southeast
wing of the WIS 44 bridge over US 41, replacements of pavement, curb and gutter, concrete median
slope noses, and sidewalk, paving brick and landscaping curb, trees and perennials, and pavement
markings.
June 10 to June 14: The contractor worked on forming and pouring the
remainder of joints and wing at the WIS 44 bridge over US 41. Concrete pavement approach slabs
were poured.
June 17 to June 21: The contractor will remove forms and complete joint
repair at the WIS 44 bridge over US 41. Pavement repairs will be completed. Landscaping and
restoration will take place and all lanes will be open to traffic by the end of the week. Project
will be shut down until work resumes August 5, 2013.
Traffic impacts: WIS 44 northbound and southbound lanes limited to one lane in
each direction with crossovers at the ramp terminal intersections. Northbound and southbound
traffic is counter-directional on the WIS 44 bridge across US 41. One travel lane will be
maintained at all times for ramps.
US 41 reconstruction over Lake Butte des Morts – US 41 major
Schedule: August 2011 to July 2013
Length: 2 miles
Cost: $54.2 million
Location: WIS 21 Interchange, US 41 mainline from 1500 feet north of Witzel
Avenue, to the US 45 Interchange.
Description: This project involves the reconstruction of the WIS 21 interchange to
pass over US 41. The interchange will be completely reconstructed to include roundabouts at ramp
terminals and at the WIS 21 intersections with Washburn and Koeller Streets. This project also
includes the reconstruction of mainline US 41 from Witzel Avenue to the US 45 Interchange including
new bridges over Lake Butte des Morts and Sawyer Creek. The work on the Lake Butte des Mort
Causeway will include a recreational trail along the east side of US 41 crossing over the water.
June 10 to June 14: Crews completed paving on the northbound lanes of US 41 over
the Lake Butte des Morts causeway. Crews continued installing parapets and railing on the main
channel bridge and staining concrete bridges throughout the project. Crews began concrete
barrier wall installation on the northbound lanes of US 41 over the Lake Butte des Morts causeway.
June 17 to June 21: Crews will continue concrete barrier wall installation on
the northbound lanes of US 41 over the Lake Butte des Morts causeway, installing parapets on the
main channel bridge and staining concrete bridges throughout the project.
Traffic impacts: The northbound and southbound shoulders of US 41 are closed
between US 45 and Witzel Avenue. Northbound and southbound US 41 are reduced to two, 11-foot lanes
in each direction between US 45 and Witzel Avenue.
US 41 Lake Butte des Morts Causeway landscaping and trail enhancements
Schedule: May to October 2013
Length: 1.5 miles
Cost: $1.45 million
Location: US 41 causeway from WIS 21 to US 45 Interchange.
Description: The work on the Lake Butte des Mort Causeway will include plantings,
kiosks, informational plaques, concrete sidewalk, walls, railings, and solar powered lighting.
June 10 to June 14: Work on the overlook railing foundations and the footings for
the railings above the fishing paths were completed. Crews continued installing kiosk
footings. Concrete sidewalk in the overlooks was started.
June 17 to June 21: Crews will finish work on the kiosk footings. Work
will continue on the concrete sidewalk in the overlooks. Topsoil and restoration landscaping will
begin around the completed overlooks.
Traffic impacts: N/A
Motorists are advised to use caution and remain alert when driving through any work zone and should:
- Buckle up for safety.
- Know where construction zones are located and allow extra time to get through them.
- Avoid the peak travel hours.
- Watch for special messages on electronic message boards as you approach major construction zones.
- Slow down, get into the correct lane early, and merge cautiously.
- Stay alert for surprise slow-downs.
- Take a scenic alternate route.
For more information regarding traffic impacts in the Northeast Region:
- Follow us on Twitter for regional alerts from the Traffic Incident Alert System and for construction related traffic advisories.
- Call 5-1-1 or visit Wisconsin 511 online.
Alerts and updates provided via these sites are not intended for use while driving. When driving, your focus should always be on driving.
For more information, contact:
Communications Manager Kim A. Rudat, WisDOT NE Region
(920) 492-5743,
kim.rudat@dot.wi.gov
Communications Manager Mark Kantola, WisDOT US 41 Project
(920) 492-4153,
mark.kantola@dot.wi.gov
| |

