St. Croix Bridge construction moves up to begin in spring 2013

October 9, 2012

The Minnesota and Wisconsin departments of Transportation announced today they will accelerate the St. Croix Bridge project by starting construction on the river piers for the bridge foundation in 2013.

"We have been working on integrating the results of the load testing to make the project more efficient in terms of managing scope, schedule and budget," said Jon Chiglo, MnDOT project director. "By separating out the foundation work, we can start construction sooner, reduce inflation costs and create jobs a year earlier than scheduled."

The $50 million contract will open for bids in late-winter 2013. Construction is anticipated to begin on the bridge foundations in late-spring 2013. Previously, construction was planned to begin in spring 2014.

The St. Croix Crossing project replaces the 80-year-old Stillwater Lift Bridge with a safer, more reliable four-lane bridge that will connect expressways on both sides of the St. Croix River in Stillwater and Oak Park Heights, Minnesota and St. Joseph, Wisconsin. The project adds extensive trail systems, including converting the Stillwater Lift Bridge to a bicycle and pedestrian crossing. It also includes constructing three miles of four-lane highway on Highway 35 in Wisconsin and reconstructing about three miles of Highway 36 and Highway 95 in Minnesota.

The four-lane St. Croix Crossing Bridge is estimated to cost between $280 million and $310 million. The total cost for the entire St. Croix Crossing project is estimated to cost between $580 million and $676 million.

For more information on the St. Croix Crossing project, visit the project web page or the St. Croix Crossing Facebook page.

For more information, contact:
Mary McFarland Brooks, Minnesota Department of Transportation
395 John Ireland Boulevard
Saint Paul, MN 55155
Tel (651) 366‐4280
Cell (651) 200-5453
Email mary.mcfarland@state.mn.us

Christine Ouellette, Wisconsin Department of Transportation
Northwest Region
718 W. Clairemont Avenue
Eau Claire, WI 54701
Tel (715) 833‐9814
Cell (715) 828‐9417
Email chris.ouellette@dot.wi.gov

 

Events

WisDOT radio newsline

Other news releases:

Law of the month

Public hearings and meetings

WisDOT media contacts