US 51 corridor, Dane County north segment - Schedule

For more information on public information meetings (PIM), hearings and other public activities, visit Public involvement.

Current

  • Final design work

Future

2012

  • July 2012 - Letting scheduled (Reardon Road – Vinburn Road)
  • September 2012 - Construction scheduled to start (Reardon Road – Vinburn Road)
  • 2012 - Construction of the 4-lane highway scheduled to start
  • 2012 and 2013 - Construction scheduled to start (north of WIS 19 - north of Vinburn Road). This construction project will include the overpasses at Bear Tree Parkway and Vinburn Road as well as the whole interchange at Windsor Road.

2013

  • September 2013 - Letting scheduled (Vinburn Road - County V)
  • Fall 2013 - Construction scheduled to be completed (Reardon Road – Vinburn Road)

2014

  • Spring 2014 - Construction scheduled to start (Vinburn Road - County V)
  • Fall 2014 - Construction scheduled to be completed (Vinburn Road - County V)
  • 2014 - Construction scheduled to start (north of Vinburn Road - Grinde Road). This construction project will include the interchange at County V, as well as the proposed County V segment.

Past

  • August 2011 - Plans submitted for first segment
  • 2010-2011 - Right of way acquisitions




DMV | Safety | Travel | Plans & Projects | State Patrol | Doing Business | Programs for Local Gov't

Air | Bicycles | Bus/transit | Cars | Motorcycles | Pedestrian | Rail | Trucks | Waterways

Home | News | About Us | Research & Library | A-Z Index | Site Survey