US 51 Expansion Project (Reardon Rd.-County V (Grinde Rd.))

Need/purpose

Schedule

Maps

FAQ

Traffic impacts

Related info.

Contacts

US 51 Expansion Project (Reardon Rd.-County V (Grinde Rd.)) - Traffic impacts

Overview | Access | Traffic stages | Camera images | Work zone safety tips

WisDOT 511 logo.

New View traffic updates, including the info. in red below, in its new location.

Closures

Rd. construction.

Reardon Rd.

  • Beginning May 13, 2013, Reardon Rd. will be closed at US 51.
  • Reardon Rd. will be rerouted to Windsor Rd. and the new Pederson Crossing Blvd. (constructed to gravel).
  • Message boards are located to the north and south of Reardon Rd. along US 51 to alert traffic to this closure.

Vinburn Rd.

  • Beginning May 20, 2013, Vinburn Rd. will be closed at US 51 to the east for a three week period.
  • Vinburn Rd. will be closed from US 51 to the east approximately 600 ft.
  • Vinburn Rd. will still have access to US 51 from the west.
  • Vinburn Rd. east will not have a posted detour. Travelers will need to find a way around.
  • Windsor Rd. will be open during the Vinburn Rd. closure.
  • Message boards will be installed along US 51 7 days prior to alert traffic to this closure.

Windsor Rd.

  • The Windsor Rd. closure can begin anytime after June 7, 2013 and will run through Sept. 27, 2013.
  • Traffic will be re-routed around the closure via a temporary Gray Rd./North Towne Rd. intersection, except for a three week period beginning the end of July.
  • School bus access will be provided through the project area for the fall semester beginning Sept. 3, 2013.
  • Windsor Rd. will be closed to the west and east of US 51, but the closure will end before the next available road to both the west and east.
  • Windsor Rd. will have a posted detour, directing travelers along Lake Rd./County CV, Vinburn Rd. and Portage Rd.
  • Message boards will be installed along US 51 seven days prior to alert traffic to this closure.

Overview

  • Construction activities can change at any time. Please check back periodically for updates and further information.
  • View the Maps page for detour routes and maps depicting traffic flow, access and work zones for each stage.

Access

  • Reardon Rd. will be provided access at all times.
  • Windsor Rd. will be detoured during the end of stage 1 and continuing into the beginning of stage 2.
  • School access
    • Windsor Rd. will not be closed until after the end of the school year, June 7, 2013.
    • School buses will be provided access through the project area beginning at the start of the fall semester, approximately Sept. 3, 2013.

Traffic stages

Camera images

View current photos from project area (view NE)

Note - Photo updates approximately every 5 minutes, thus this page is set to refresh itself (or you may try refreshing the browser) every 5 minutes so the most current image is available for viewing.

US 51/WIS 19 camera image.

Camera images from WisDOT camera located at US 51/WIS 19 (view NE).

All closures are dependent on favorable weather conditions. Please drive with caution through work zones.

Work zone safety tips

  • Buckle up for safety
  • Expect the unexpected
  • Stay alert
  • Watch for flagging operations
  • Merge as soon as possible
  • Don't speed. Remember, fines double in work zones
  • Don't tailgate
  • Keep a safe distance
  • Observe posted signs
  • Be patient

Top Return to top


DMV | Safety | Travel | Plans & Projects | State Patrol | Doing Business | Programs for Local Gov't

Air | Bicycles | Bus/transit | Cars | Motorcycles | Pedestrian | Rail | Trucks | Waterways

Home | News | About Us | Research & Library | A-Z Index | Site Survey