WIS 21 Planning Study - Schedule

For more information on public information meetings (PIM), hearings and other public activities, visit Public involvement.

Current

 

Past

2011

  • Fall 2011 - Present preferred alternative
  • Fall 2011 - Transporation project plat
  • Early 2011 - Local officials and stakeholder committee meeting

2010

  • Late 2010 - PIM
  • Summer 2010 - Local officials and stakeholder committee meeting

2009

  • Late 2009-Early 2010 - PIM
  • Fall 2009 - Local officials and stakeholder committee meeting

2008

  • Fall 2008-Summer 2009 - Alternatives analysis

2006

  • Summer 2006-Fall 2008 - Systems interchange feasibility review
  • Early 2006 - PIM

2005

  • Late 2005-early 2006 - Alternatives development
  • Fall 2005 - Stakeholder committee meeting

2004

  • Fall 2004-early 2005 - Traffic analysis
  • Fall 2004 - Stakeholder committee meeting
  • Fall to late 2004 - Data gathering

Major steps in preparing the plan include:

  • Gathering information such as traffic volumes, crash data, existing land use and environmental characteristics.
  • Determining future land use and travel demand.
  • Determining transportation and community needs.
  • Developing transportation improvement alternatives.
  • Analyzing transportation improvement alternatives to determine their ability to meet the WIS 21 goal and objectives.
  • Preparing alternative concept drawings for corridor improvements.

Top Return to top



DMV | Safety | Travel | Plans & Projects | State Patrol | Doing Business | Programs for Local Gov't

Air | Bicycles | Bus/transit | Cars | Motorcycles | Pedestrian | Rail | Trucks | Waterways

Home | News | About Us | Research & Library | A-Z Index | Site Survey