WIS 22 (Main St.), 10th St.-WIS 156 - Schedule

For more information on Public Involvement Meetings (PIM), hearings and other public activities, visit Public involvement.

Current (this year)

  • No meetings currently scheduled

Future (next year and beyond)

  • Early 2014 - “In This Together” business meeting planned
  • Early 2015 - Construction information meeting planned
  • Feb. 2014 - Final roadway plans scheduled for completion for the segment between 10th and 13th streets
  • June 2015 - Final roadway plans scheduled for completion for the segment between 13th St. and WIS 156
  • 2015 - Work on Pigeon River Bridge, and the roadway between 10th and 13th streets currently scheduled for construction
  • 2017 - The section of roadway between 13th St. and WIS 156/Green Tree Rd. currently scheduled for construction, but may occur as early as 2016


Past (anything prior to today)

2013

  • Nov. 14, 2013 - PIM
  • Oct. 14, 2013 - Local officials meeting
  • Aug. 2013
    • Environmental documentation completed
    • Preliminary roadway plans completed
    • Right of way plats completed

2012

  • Oct. 10, 2012 - Local officials meeting
  • Oct. 22, 2012 - PIM
  • Summer 2012 - Historical and archaeological surveys completed

SSI - Project contacts Questions about the content of this page:
WisDOT North Central Region Office, ncr.dtsd@dot.wi.gov
Last modified: January 10, 2014

All external hyperlinks are provided for your information and for the benefit of the general public. The Wisconsin Department of Transportation does not testify to, sponsor or endorse the accuracy of the information provided on externally linked pages. Some pages contain links to other documents and media types (PDF, Word, Flash, Video, etc.) and require free plugins to work. Visit our software information page for assistance.