Need/purpose

Schedule

Maps

Environmental documents

Public involvement

Traffic impacts

Contacts

Business 51 (Post Road) - Schedule

For information on public information meetings (PIM), hearings and other public activities, visit Public involvement.

Current

  • Final design work for Green Dr. to Springville Dr. is under way and scheduled for completion in 2014.

Future

  • Construction currently scheduled to start from Green Drive to Sprinville Dr. in 2016

Past

  • Oct. 26, 2011 - Local office hours 9:30 a.m. - 4:30 p.m.
  • Oct.26, 2011 - Business owners meeting
  • Oct. 19, 2011 - PIM
  • Oct.5, 2011 - Local officials meeting

  • Mid-Sept. 2011 - Business 51/Minnesota Avenue intersection improvements completed
  • Jan. 26, 2011 - PIM
  • Summer 2011 - Construction started, Business 51/Minnesota Avenue intersection
  • July 22, 2011 - Business 51 in the village of Whiting reopened to traffic
  • Jan. 19, 2011 - Local officials meeting

2010 and older

  • 2010 - Preliminary design work started, Portage County B to Minnesota Avenue
  • 2009 - Environmental document completed
  • October 2004 - Corridor study completed
  • 2002 - Planning started


Sign up for email updates

Related information

'In This Together' program  - Information for businesses located in work zones

 


DMV | Safety | Travel | Plans & Projects | State Patrol | Doing Business | Programs for Local Gov't

Air | Bicycles | Bus/transit | Cars | Motorcycles | Pedestrian | Rail | Trucks | Waterways

Home | News | About Us | Research & Library | A-Z Index | Site Survey