WIS 29 (County FF-County U) Freeway Conversion

Need/purpose

Schedule

Maps

FAQ

Environmental documents

Public involvement

Contacts

WIS 29 (County FF-County U) Freeway Conversion

Location | Overview | Status/phase

 

Project location

WIS 29, County FF - County U, through villages of Hobart and Howard, in Brown and Outagamie counties.

WIS 29 (County FF-County U) Freeway Conversion - Project overview/location map.Map key - Thick orange line is the project overview/location. Blue tear drop with dot in center is the project boundary.

View NE, WIS 29 (County FF-County U) Freeway Conversion maps.

Project overview

Preparing preliminary and final plans to implement recommendations from the WIS 29 Corridor Preservation Plan (2008) to identify the improvements necessary to convert WIS 29 from an expressway to a freeway and to restrict access elsewhere along the corridor.

Recommendations were developed with the cooperation of area residents and officials.

  • Constructing interchanges at County VV and County FF
  • Building overpasses at County U and North Pine Tree Rd.
  • Closing Sunlite Dr. and Woodland Rd. intersection

WIS 29 is designated as a Backbone route. The highway serves interstate and inter-regional trips and functions as the primary route across north-central Wisconsin, linking Green Bay with I-94 and Minneapolis/St. Paul.

Current traffic volumes make WIS 29 the state’s most heavily traveled east-west highway north of I-94. These traffic volumes also indicate that a large amount of truck traffic travels WIS 29, highlighting the highway’s importance to Wisconsin’s industry, business and agriculture.

This project has been split into two projects:

Project I (Funding approved)

  • WIS 29/County FF intersection - Design for converting to a diamond interchange
  • WIS 29/County FF interchange ramps - Roundabout
  • Golden Pond Park Ct. - Access to be relocated
  • WIS 29/Sunlite Dr./Woodland Rd. intersection - Woodland Rd. and Sunlite Dr. to be relocated to close this intersection with WIS 29
  • WIS 29/Catherine Dr. - Cul-de-sac to be designed at Catherine Dr., east of Woodland Rd./Sunlite Dr.
  • County FF/Golden Pond Park Ct./Navajo Trail - Roundabout
  • Sherwood St./Shawano Ave. (County C) - Roundabout

View maps and more info. on Project I

Total cost (including real estate/utilities/construction engineering) estimated at $13,500,000.

Project II (Funding has not been approved)

  • WIS 29/County VV intersection - Design for converting to a diamond interchange
  • WIS 29/North Pine Tree Rd. - Current Pine Tree Rd. to be extended over WIS 29
  • Milltown Rd. - Realignment
  • Old Highway 29 - Realignment
  • WIS 29/County U - Overpass

View maps and more info. on Project II

Total cost (including real estate/utilities/construction engineering) estimated at $27,100,000.

Status/phase

Project I

  • Funding approved
  • Preliminary and final design work with real estate acquisition planned 2012
  • Construction scheduled to start fall 2013 and be completed fall 2014

Project II

  • Funding has not been approved
  • WisDOT is moving forward with preparation of construction plans to allow these improvements to be constructed as soon as funding becomes available
  • Real estate acquisition will not begin on these portions of the project until construction funding is secured

Top Return to top

WIS 29 roadway sign.

Related information

'In This Together' program - Info. for businesses located in work zones

Life of a highway project

Village of Hobart

Village of Howard

 


DMV | Safety | Travel | Plans & Projects | State Patrol | Doing Business | Programs for Local Gov't

Air | Bicycles | Bus/transit | Cars | Motorcycles | Pedestrian | Rail | Trucks | Waterways

Home | News | About Us | Research & Library | A-Z Index | Site Survey