WIS 13 Red Cliff Project - Fast facts
Bayfield to Red Cliff, Bayfield County

View NW, WIS 13 Red Cliff Project - Bayfield to Red Cliff in a larger map
Map key - Thick orange line is the project overview/location, yellow line is detour route, and the blue tear drop with dot in center are the project limits.
Wisconsin 511 travel information

Location

WIS 13, 7th Street (city of Bayfield) to Old County K (Red Cliff), in Bayfield County.

The project is expected to start on May 13, 2013. The detour will go into effect May 14, 2013.

Overview

  • Resurface with new asphalt.
  • Replacing curb and gutter
  • Replacement and addition of new street lighting in city of Bayfield.
  • Replacement of all permanent highway signing.

Promote your business during construction

Come In We're Open sign

Is your business located within ½ mile of the WisDOT construction zone for this project? If so, help your business not only survive, but thrive, during the construction project. Promote your business by uploading your business information to our business listing website.

Schedule

  • Project is expected to begin early May, possibly late April, weather permitting.
  • June 2013 - Interim completion date for the work from Broad to 1st Streets in city of Bayfield.
  • August 1, 2013 - Project completion.

Construction update

Anticipated work schedule for the week of: May 13, 2013

  • Placement of traffic control and detour signs on Monday.

  • Sawing will start on Tuesday after warning signs are up

  • Xcel Energy will be removing existing street lights after detour is active.

Traffic impacts/Detours

  • Traffic will be maintained using single lane closures and flaggers for much of the project work.
  • There will be a detour of WIS 13 traffic in city of Bayfield while the work is being done from Broad to 1st Streets.
    • The detour is on 6th Street and Washington Avenue and will begin May 13 until May 27, 2013
  • Work zone and detour route map

Contact information

Chris Ouellette, WisDOT Northwest Region Communications Manager
(715) 833-9814
chris.ouellette@dot.wi.gov

Phil Keppers, WisDOT Project Manager
(715) 395-3027
phil.keppers@dot.wi.gov

Wisconsin Department of Transportation (WisDOT)
Northwest Region, Eau Claire Office
718 W. Clairemont Ave.
Eau Claire WI
Phone (715) 836-2891 or toll-free (800) 991-5285
Fax: (715) 392-7863
WI Telecommunications Relay System (TTY): 711
Email: nwr.dtsd@dot.wi.gov

Server side include - Who to contact about the content of this page Questions about the content of this page, contact:
WisDOT Northwest Region Office, nwr.dtsd@dot.wi.gov
Last modified: May 8, 2013

All external hyperlinks are provided for your information and for the benefit of the general public. The Wisconsin Department of Transportation does not testify to, sponsor or endorse the accuracy of the information provided on externally linked pages. Some pages contain links to other documents and media types (PDF, Word, Flash, Video, etc.) and require free plugins to work. Visit our software information page for assistance.