US 2, Bong Bridge - Fast facts
City of Superior - Douglas County

View NW, US 2 Bong Bridge in city of Superior - Douglas County in a larger map.
Map key - Thick orange line is the project overview/location. Blue tear drop with dot in center is the project limit.
Wisconsin 511 travel information

Location

US 2, in city of Superior (from the Belknap Viaduct to I-35 in Minnesota), in Douglas County.

Overview

WisDOT will be making several improvements on US 2, in the city of Superior, in 2014 and 2015.

Bong Bridge work

  • Overlay existing bridge deck and make necessary repairs to the sidewalk
  • Replace and repair arch components and repaint
  • Replace existing expansion joints and repaint girder ends
  • Replace street lights and ship navigation lights

Wisconsin approach

  • Reconfigure the existing Belknap St. and US 2 intersection to a modern roundabout
  • Add local access connection to US 2 for North Garfield Ave. (city industrial park)
  • Bridge deck overlay of the Susquehanna overhead bridge
  • Replace roadway lighting
  • Replace existing concrete pavement

Promote your business during construction

Come In We're Open sign

Is your business located within ½ mile of the WisDOT construction zone for this project? If so, help your business not only survive, but thrive, during the construction project. Promote your business by uploading your business information to our business listing website.

Schedule

  • Construction of westbound US 2 to begin spring/early summer 2014
  • Construction suspended Nov. 2014-Apr. 2015 (US 2 open to both eastbound and westbound travel over the winter)
  • Construction of eastbound US 2 to begin May 2015
  • Project completed Nov. 2015

Traffic impacts/Detours

  • May-Nov. 2014, westbound traffic detoured to Blatnick Bridge
  • May-Nov. 2015, eastbound traffic detoured to Blatnick Bridge

Status

Construction 2014-2015

Contact information

Chris Ouellette, WisDOT Northwest Region Communications Manager
(715) 833-9814
chris.ouellette@dot.wi.gov

Matt Dickenson, WisDOT Project Manager
(715) 395-3022
matthew.dickenson@dot.wi.gov

Wisconsin Department of Transportation (WisDOT)
Northwest Region, Superior Office
1701 N. 4th St.
Superior, WI 54880
Phone: (715) 392-7925
Fax: (715) 392-7863
TDD: (800) 590-1868
WI Telecommunications Relay System (TTY): 711
Email: nwr.dtsd@dot.wi.gov

Server side include - Project contacts Questions about the content of this page, contact:
WisDOT Northwest Region Office, nwr.dtsd@dot.wi.gov
Last modified: April 10, 2013

All external hyperlinks are provided for your information and for the benefit of the general public. The Wisconsin Department of Transportation does not testify to, sponsor or endorse the accuracy of the information provided on externally linked pages. Some pages contain links to other documents and media types (PDF, Word, Flash, Video, etc.) and require free plugins to work. Visit our software information page for assistance.