WIS 93 Revitalization - Fast facts
Independence, Trempealeau County

Wisconsin 511 travel information
View NW, WIS 93 Revitalization - Independence, Trempealeau County in a larger map.
Map key - Thick orange line is the project overview/location. Blue tear drop with dot in center is the project limit.

The next public involvement meeting will be held at 5 p.m. Monday, September 15, at the Opera House located within City Hall.

Location

WIS 93, A St. to Indee Blvd., in Independence, in Trempealeau County.

Overview

  • We are currently reconstructing WIS 93 in Independence. Additional improvements will include:
    • Reconstructing the WIS 93/WIS 121 intersection (including the addition of turn/auxiliary lanes)
    • Upgrading the existing storm sewer and street lighting
    • Replacing outdated sanitary and water utilities
    • Replacing Elk Creek Bridge

Promote your business during construction

Come In We're Open sign

Is your business located within mile of the WisDOT construction zone for this project? If so, help your business not only survive, but thrive, during the construction project. Promote your business by uploading your business information to our business listing website.

Schedule

  • Stage 2 is underway - June 4-November 26, 2014
    • Work consists of reconstructing WIS 93 between A Street and WIS 121. WIS 93 north of the WIS 121 intersection will be open to all through traffic.

Traffic impacts/Detours

  • WIS 93 between A St. and WIS 121 is detoured via WIS 95 to US 53 to WIS 121.
  • The roadway between Adams Street/County Q (North) and Elm Street, including the bridge, is open to local traffic only.
    • The roadway is not open to through traffic between Elm Street and WIS 121.
    •  Local Traffic is expected to use the local street system to gain access though the city.
  • Truck traffic is not allowed on any of the city streets.
  • View detour map

Construction update: Week of September 1, 2014

  • Underground utility work will continue.
  • Grading will continue in preparation for concrete pavement.
  • Concrete pavement is scheduled to be place September 8.

Status/phase

Project scheduled to be completed November 26, 2014.

Contact information

Dave Koepp, WisDOT Project Manager
(715) 836-2078
david.koepp@dot.wi.gov

Chris Ouellette, WisDOT Northwest Region Communications Manager
(715) 833-9814
chris.ouellette@dot.wi.gov

Wisconsin Department of Transportation (WisDOT)
Northwest Region, Eau Claire Office
718 W. Clairemont Ave.
Eau Claire WI
Phone (715) 836-2891 or toll-free (800) 991-5285
Fax: (715) 392-7863
Email: nwr.dtsd@dot.wi.gov

SSI - Project contacts Questions about the content of this page:
WisDOT Northwest Region Office, nwr.dtsd@dot.wi.gov
Last modified: August 28, 2014

All external hyperlinks are provided for your information and for the benefit of the general public. The Wisconsin Department of Transportation does not testify to, sponsor or endorse the accuracy of the information provided on externally linked pages. Some pages contain links to other documents and media types (PDF, Word, Flash, Video, etc.) and require free plugins to work. Visit our software information page for assistance.