I-43 (Silver Spring Dr.-WIS 60) North-South Corridor - Schedule

For more info. on public information meetings (PIM), hearings and other public activities, visit Public involvement.

Schedule (printable version) PDF

Current

  • 2012 - Agency Coordination started
  • August 2012 - PIM scheduled to discuss project
  • November 2012 - Initial Alternatives Development

Future

2013

  • Jan./Feb. 2013 - Anticipated PIM scheduled
  • July/Aug. 2013 - Anticipated PIM scheduled
  • Summer 2013 - Anticipated screened alternatives
  • Fall 2013 - Anticipated recommended alternatives

2014

  • 2014 - Anticipated agency coordination completed
  • Feb. 2014 - Anticipated Public Hearing regarding project
  • Winter 2014 - Anticipated Draft of Environmental Impact Statement (EIS)
  • Spring 2014 - Anticipated Final of Environmental Impact Statement (EIS)
  • Fall 2014 - Anticipated Functional plans of alternative development
  • Fall 2014 - Anticipated Record of Decision (ROD) Environmental Clearance

Past

  • 2012 - Data Gathering

 


 

 


DMV | Safety | Travel | Plans & Projects | State Patrol | Doing Business | Programs for Local Gov't

Air | Bicycles | Bus/transit | Cars | Motorcycles | Pedestrian | Rail | Trucks | Waterways

Home | News | About Us | Research & Library | A-Z Index | Site Survey