US 12 Corridor, aka Baraboo Bypass - Schedule

For more information on Public Involvement Meetings (PIM), hearings and other public activities, view each project section's public involvement page.

Project section schedules

Current (this year)

  • Spring 2015 - South section construction scheduled to start

Future (next year and beyond)

  • Fall 2017 or later - South section, construction scheduled to be completed


Past (anything prior to today)

2014

  • Fall 2014 - Bike/pedestrian accommodations, construction completed
  • Aug. 2014 - Bike/pedestrian accommodations, construction scheduled to start

2011

  • Fall 2011 - North section, construction completed

2010 and older

  • Jan. 2010 - PIM
  • Spring of 2009 - North section, construction started
  • Feb. 2008 - PIM, south section
  • Nov. 2007 - PIM
  • 2007 - South section, design work started

  • May 2006 - PIM
  • Apr. 2005 - PIM
  • 2005 - North section, design work started
  • Oct. 2004 - EIS approved
  • 1994 - Environmental Impact Statement (EIS) started

Questions about the content of this page, contact:
WisDOT Southwest Region Office-Madison, swr.dtsd@dot.wi.gov
Last modified: March 25, 2015

All external hyperlinks are provided for your information and for the benefit of the general public. The Wisconsin Department of Transportation does not testify to, sponsor or endorse the accuracy of the information provided on externally linked pages. Some pages contain links to other documents and media types (PDF, Word, Flash, Video, etc.) and require free plugins to work. Visit our software information page for assistance.