US 14 Reconstruction - Schedule

Existing US 14.

For more information on Public Involvement Meetings (PIM), hearings and other public activities, visit Public involvement.

Current (this year)

  • Nov. 2014 - PIM tentatively scheduled for Park and ride lot (Segment F) preliminary design plans and tentative schedule.
  • 2014-2017 - Design work continues
    • US 14 Realignment (Segment E)
    • Park and ride lot (SE quadrant of the US 14/WIS 138 interchange) (Segment F)
    • Existing US 14 Rehabilitation, W. Rutland Rd. to WIS 138 (Segment I)

Future (next year and beyond)

2018-2024

  • US 14 Realignment (Segment E) construction
    • Phases of the project to be constructed over the next four to six years
  • Park and ride lot (Segment F) construction anticipated, specific year TBD
  • Existing US 14 Rehabilitation, W. Rutland Rd. to WIS 138 (Segment I), construction
    anticipated 2024


Past (anything prior to today)

2014

2013 - Design work started

  • US 14, WIS 92 to WIS 138 (Segment E)
  • Park and ride lot (Segment F)

2012 - Reconstruction of the US 14 and County MM interchange and County MM and County M
intersection completed (Segment D)

2011

  • Reconstruction of US 14 and WIS 138 interchange completed (Segment B)
  • City of Fitchburg project reconstruction phase of the placement of existing Lacy Road Overpass and McCoy Road interchange completed (Segment G)
  • Resurface US 14 from US 12/18 to County MM completed (Segment C)
  • PIMís
    • May 12, 2011 - PIM for US 14 and County MM interchange and County MM and County M
      intersection
    • Jan. 25, 2011 - PIM for WIS 138 and US 14 interchange
    • Jan. 25, 2011 - PIM to inform the community of the anticipated US 14 and WIS 138 interchange
      project construction duration, staging and traffic re-routing.

2010 - City of Fitchburg resurfaced the 4-lane segment on McCoy Road in the interchange area
(Segment G)

2009 - Reconstructed and expanded US 14 to four lanes from County MM to WIS 138 (Segment A)

Aug. 14, 2008 - Public hearing for the US 14 corridor projects (Segments A, B, C and E)

2006 - PIM for the US corridor projects (Segments A, B, C and E)

2005 - Resurfacing existing US 14 from West Rutland road to WIS 138 (Segment H)

Questions about the content of this page:
WisDOT Southwest Region Office-Madison, swr.dtsd@dot.wi.gov
Last modified: October 13, 2014

All external hyperlinks are provided for your information and for the benefit of the general public. The Wisconsin Department of Transportation does not testify to, sponsor or endorse the accuracy of the information provided on externally linked pages. Some pages contain links to other documents and media types (PDF, Word, Flash, Video, etc.) and require free plugins to work. Visit our software information page for assistance.