US 51, McFarland-DeForest - ScheduleCars exiting Stoughton Road (US 51).

For more info. on public information meetings (PIM), hearings and other public activities, visit Public involvement.

No major construction projects are planned at this time.

Current (this year)

  • June 2013 - DRAFT EIS (DEIS) anticipated to be completed
  • July 2013 - Public hearing anticipated on DEIS
  • Aug. 2013 - Preferred alternative selection anticipated
  • Sept. 2013 - PIM anticipated, present preferred alternative
  • Dec. 2013 - Final EIS (FEIS) anticipated to be completed

Future (next year and beyond)

  • May 2014 - Anticipate Record of Decision (ROD) issued and completion of study

Past (everything prior to today)

2013

2012

  • Items started in 2012
    • Update crash data traffic operations and modeling data
    • Review and refine/update alternatives developed as part of the TSNIA
    • Analyze and assess impacts of updated alternatives
  • Aug. 14, 2012 - PIM to reacquaint the public with the project and work completed as part of the Traffic, Safety and Needs Identification Analysis (TSNIA) and provide info. regarding the new study

2011

  • Nov. 2011 - Transportation Projects Commission (TPC) approved the corridor for an Environmental Impact Study (EIS)

Mar. 2004 - Spring 2012

  • TSNIA corridor study to develop long-term planning alternatives to address issues identified in the Needs Assessment (NA), including:
    • Improving safety
    • Reducing congestion
    • Improving bicycle, pedestrian and transit facilities
    • Reducing diversion to neighborhood streets
    • Supporting economic development
  • Developed draft alternatives
  • Assessed impacts
  • Traffic modeling
  • Public involvement
    • Community events
    • Focus groups
    • Workshops
    • PIMs

Oct. 2001 - June 2003

  • NA conducted on the corridor to identify corridor deficiencies and needs:
    • Neighborhood, business, bicycle/pedestrian focus groups
    • Public opinion survey
    • PIMs

DMV | Safety | Travel | Plans & Projects | State Patrol | Doing Business | Programs for Local Gov't

Air | Bicycles | Bus/transit | Cars | Motorcycles | Pedestrian | Rail | Trucks | Waterways

Home | News | About Us | Research & Library | A-Z Index | Site Survey