WIS 26 Corridor - Expansion project, Segment 5 (Jefferson bypass)

Project overview

Segment 5 consists of constructing a 7.5-mile freeway to carry WIS 26 traffic around the west side of the city of Jefferson. The new highway will be expanded to two lanes in each direction with a grass median.

Three interchanges will be constructed, one on the south side of Jefferson, one at US 18 and one on the north side of Jefferson. Bridges will be constructed at County W, County J, Popp Road, County N and Jahn Road to provide through travel under or over WIS 26.

The section of existing WIS 26 through the city of Jefferson will be jurisdictionally transferred to local government when the new bypass is opened to traffic.

The estimated construction cost is $56.6 million (in 2008 dollars).

Schedule

Real estate acquisition is scheduled to start in late 2006.

Construction of this segment was started in 2008 is scheduled to be completed in 2011.

Maps

Project overview/location

Map of WIS 26 Corridor segment 5.

The following documents are in Adobe PDF PDF format.
(Note: Some files are large and may take longer to download depending on individual connection speeds. Users may need to zoom in to see details.)

Public information meetings (PIM) and hearings

Scheduled/future

  • There are no scheduled meetings to report on at this time.

Past meetings

  • May 17, 2007 - PIM
  • April 12, 2006 - PIM
  • October 26, 2005 - PIM

Newsletters/handouts

Back Back to WIS 26 Expansion Project

Top Return to top

WIS 26 expansion project segments:

Segment 1 - Janesville to Milton

Segment 2 - WIS 59 relocation at Milton

Segment 3 - Milton to Fort Atkinson

Segment 4 - Fort Atkinson bypass

Segment 5 - Jefferson bypass

Segment 6 - Jefferson to Johnson Creek

Segment 7 - Johnson Creek to Watertown

Segment 8 - Watertown to WIS 60 East

 


DMV | Safety | Travel | Plans & Projects | State Patrol | Doing Business | Programs for Local Gov't

Air | Bicycles | Bus/transit | Cars | Motorcycles | Pedestrian | Rail | Trucks | Waterways

Home | News | About Us | Research & Library | A-Z Index | Site Survey